September 2013
Report presented to Council for a decision regarding the approval or otherwise of the event leases
Report presented to Council for a decision regarding the approval or otherwise of the event leases
23 January 2014
The GOUD 2014: If approved, event construction is scheduled
The GOUD 2014: If approved, event construction is scheduled
02 February 2014
Adelaide Fringe 2014: If approved, event construction is scheduled
Adelaide Fringe 2014: If approved, event construction is scheduled
09 February 2014
Gluttony 2014: If approved, event construction is scheduled
Gluttony 2014: If approved, event construction is scheduled
11 February → 15 March 2014
Adelaide Fringe 2014: Proposed event to be staged
Adelaide Fringe 2014: Proposed event to be staged
12 February → 15 March 2014
The GOUD 2014: Proposed event to be staged
The GOUD 2014: Proposed event to be staged
13 February → 15 March 2014
Gluttony 2014: Proposed event to be staged
Gluttony 2014: Proposed event to be staged
18 March 2014
Gluttony 2014: Infrastructure to be removed
Gluttony 2014: Infrastructure to be removed
20 March 2014
Adelaide Fringe 2014: Infrastructure to be removed
Adelaide Fringe 2014: Infrastructure to be removed
30 March 2014
The GOUD 2014: Infrastructure to be removed
The GOUD 2014: Infrastructure to be removed