Project Timeline

Engagement will be undertaken in stages with the following associated timelines.


Stage 1: Between 22 October 2021 and 12 November 2021

The first step is to engage the community on levels of service for Park Lands and Open Space and Streets and Transportation. This will include intercept and targeted surveys, as well as online consultation through this platform. Click here to complete the survey.

Stage 2: Early 2022

A second stage of consultation will follow in early 2022, focusing on the levels of service for the remaining four asset categories.

Stage 3: Early 2022

The feedback from the two prior consultations on the levels of service will be used to draft the six Asset Management Plans (AMPs). It is envisaged that initially two draft AMPs will go out for community consultation as draft documents for final comment in early 2022. Once endorsed, these two AMPs will be incorporated into the Annual Business Plan and Budget 2022-2023.

Council will undertake a 21-day public consultation as per legislative requirement (Local Government Act 1999 (SA)).

Stage 4: Early 2023

The remaining four AMPs will go out for community consultation as draft documents for final comment in early 2023. Once endorsed, these four AMPs will be incorporated into the Annual Business Plan and Budget 2023-2024.

Council will undertake a 21-day public consultation as per legislative requirement (Local Government Act 1999 (SA)).