City of Adelaide: City Works Permit Applications

Have your say on City Works Permits Applications in the City of Adelaide


Current Consultations:

Hindmarsh Construct: Closure of road outside 293 - 297 Pirie Street from *12am, 12 October 2019 to 12am, 13 October 2019

(*dates and times may be changed to 12.00 am 19 October 2019 to 12.00 am 20 October 2019)

Consultation will be open for 21 days from 26 August to 5pm, 16 September 2019.

For further information - see below:

Information Pack


Project updates

ProjectConsultation periodOutcome
Hindmarsh Construct: The road closure of Pirie Street directly in front of 293 - 297 Pirie Street from 12am *12 October 2019 to 12 am 13 October 2019.
26 August 2019 to 5pm, 16 September 2019.No decision at this stage.
Traffic Group Australia: The road closure of North Terrace (east bound only) for works at the Adelaide Casino from 5am – 6pm *18 August 2019, and 5am – 6pm *31 August 2019.

22 July 2019 - 5pm, 12 August 2019.
Permits approved
Synergy: 124 Waymouth Street (closure of Tatham st; Cannon St and Eliza St: 12 July - 14 July 2019.19 June - 10 July 2019Permit approved
Traffic Group Australia: Part closure Franklin St from 21 June - 23 June 201929 May - 19 June 2019Permit approved
Minuzzo: Closure of East Tce at 217 East Tce from 10 May 19 - 28 march 202018 April - 9 May 2019Project reconfigured: Road remained open
Hindmarsh Constructions: Closure of Market St from30 March - 31 March 2019.6 March - 27 March 2019Permit approved
Built Environs: Wingfold Tower: Part closure of Waymouth St from 16 March - 17 March 201913 February - 14 March 2019Permit approved
Built: Part closure of Franklin St from 22 March - 24 March 201927 February - 20 March 2019Permit approved
Built Environs: 116 Waymouth St: Installation of construction hoarding requiring Playhouse Lane to become one-way13 February - 6 March 2019Permit approved
Synergy Construct: Toms Court: installation of construction hoarding6 February - 27 February 2019Developer working with stakeholders
John Holland: Construction works in Hurtle St and Pulteney St19 December 2018 - 9 January 2019Permit Approved
Synergy Construct: Closure Gray St from 10 December to 20 December 201810 October - 31 October 2018Permit approved: work was pushed back to 25 March and 3 April 2019.
Palumbo PTY Ltd: Part closure: Currie St. 1 Sept - 1 Dec 2018.
1 August - 22 August 2018
Permit Approved.
Cesar Federici: Partial road closure: Waymouth Street: Aug 2018.
18 July - 8 August 2018
Permit Approved


Background

Before granting an authorisation or permit, CoA is legislatively required under Section 223 of The Local Government Act 1999 (SA)to consult the public following receipt of an application for a CWP for works 'that would result in any part of a road being fenced, enclosed or partitioned so as to impede the passage of traffic to a material degree'.


Have your say on City Works Permits Applications in the City of Adelaide


Current Consultations:

Hindmarsh Construct: Closure of road outside 293 - 297 Pirie Street from *12am, 12 October 2019 to 12am, 13 October 2019

(*dates and times may be changed to 12.00 am 19 October 2019 to 12.00 am 20 October 2019)

Consultation will be open for 21 days from 26 August to 5pm, 16 September 2019.

For further information - see below:

Information Pack


Project updates

ProjectConsultation periodOutcome
Hindmarsh Construct: The road closure of Pirie Street directly in front of 293 - 297 Pirie Street from 12am *12 October 2019 to 12 am 13 October 2019.
26 August 2019 to 5pm, 16 September 2019.No decision at this stage.
Traffic Group Australia: The road closure of North Terrace (east bound only) for works at the Adelaide Casino from 5am – 6pm *18 August 2019, and 5am – 6pm *31 August 2019.

22 July 2019 - 5pm, 12 August 2019.
Permits approved
Synergy: 124 Waymouth Street (closure of Tatham st; Cannon St and Eliza St: 12 July - 14 July 2019.19 June - 10 July 2019Permit approved
Traffic Group Australia: Part closure Franklin St from 21 June - 23 June 201929 May - 19 June 2019Permit approved
Minuzzo: Closure of East Tce at 217 East Tce from 10 May 19 - 28 march 202018 April - 9 May 2019Project reconfigured: Road remained open
Hindmarsh Constructions: Closure of Market St from30 March - 31 March 2019.6 March - 27 March 2019Permit approved
Built Environs: Wingfold Tower: Part closure of Waymouth St from 16 March - 17 March 201913 February - 14 March 2019Permit approved
Built: Part closure of Franklin St from 22 March - 24 March 201927 February - 20 March 2019Permit approved
Built Environs: 116 Waymouth St: Installation of construction hoarding requiring Playhouse Lane to become one-way13 February - 6 March 2019Permit approved
Synergy Construct: Toms Court: installation of construction hoarding6 February - 27 February 2019Developer working with stakeholders
John Holland: Construction works in Hurtle St and Pulteney St19 December 2018 - 9 January 2019Permit Approved
Synergy Construct: Closure Gray St from 10 December to 20 December 201810 October - 31 October 2018Permit approved: work was pushed back to 25 March and 3 April 2019.
Palumbo PTY Ltd: Part closure: Currie St. 1 Sept - 1 Dec 2018.
1 August - 22 August 2018
Permit Approved.
Cesar Federici: Partial road closure: Waymouth Street: Aug 2018.
18 July - 8 August 2018
Permit Approved


Background

Before granting an authorisation or permit, CoA is legislatively required under Section 223 of The Local Government Act 1999 (SA)to consult the public following receipt of an application for a CWP for works 'that would result in any part of a road being fenced, enclosed or partitioned so as to impede the passage of traffic to a material degree'.


  • Traffic Group Australia: road closure of North Terrace (east bound only) for works at the Adelaide Casino: August.

    about 1 month ago

    The City of Adelaide (CoA) sought feedback on an application for a City Works Permit (CWP) submitted by Traffic Group Australia for:

    The road closure of North Terrace (east bound only) for works at the Adelaide Casino from:

    • 5.00 am – 6.00pm *18 August 2019, and
    • 5.00 am – 6.00pm *31 August 2019.

    (*the date and duration of works may be subject to variation at any time).

    Consultation was open from 22 July 2019 - 5pm, 12 August 2019.


    The City of Adelaide (CoA) sought feedback on an application for a City Works Permit (CWP) submitted by Traffic Group Australia for:

    The road closure of North Terrace (east bound only) for works at the Adelaide Casino from:

    • 5.00 am – 6.00pm *18 August 2019, and
    • 5.00 am – 6.00pm *31 August 2019.

    (*the date and duration of works may be subject to variation at any time).

    Consultation was open from 22 July 2019 - 5pm, 12 August 2019.


  • 217 East Terrace

    2 months ago

    Thank you for taking the time to provide your feedback regarding the development at 217 East Terrace, Adelaide. We apologise for the delay in coming back to you with an update.

    As a result of the consultation, we recognise that concerns from local residents are primarily focused around 3 main aspects of the current development site:

    • the potential impacts of closing East Terrace
    • the noise and disturbance generated from the speed humps
    • the loss of on-street parking as a result of the site set up

    Council’s primary focus has always been to maintain the highest level...

    Thank you for taking the time to provide your feedback regarding the development at 217 East Terrace, Adelaide. We apologise for the delay in coming back to you with an update.

    As a result of the consultation, we recognise that concerns from local residents are primarily focused around 3 main aspects of the current development site:

    • the potential impacts of closing East Terrace
    • the noise and disturbance generated from the speed humps
    • the loss of on-street parking as a result of the site set up

    Council’s primary focus has always been to maintain the highest level of safety and accessibility for the site and the local area. We strive to mitigate the impacts felt by the local community whilst also recognising our role in supporting the growth and development of our City.

    Since the consultation period closed on the 9th of May, we have been in negotiations with the developer to try and reach a resolution that takes in to consideration the concerns of all stakeholders.

    As a result of the feedback and after negotiations with the developer, we can now advise that the developer has agreed to remove the speed humps and allow the road to remain open. This will involve the installation of a pedestrian refuge which aims to encourage drivers to reduce their speed when travelling through the site, whilst also providing increased safety to pedestrians and site workers crossing the road. This is to be installed on Saturday 1st June 2019.

    In relation to the loss of on-street parking, our Parking and Information Officers have increased their monitoring of the area to ensure that parking controls are being adhered to. We will also conduct a review of the on-street parking once the new traffic management is in place. We are investigating whether there are alternative temporary arrangements we can put in place to facilitate access of on-street parking to residents and their visitors.

    Once again, we apologise that this has taken some time to come to this resolution. If you would like further information please contact us on 8203 7203.


  • Synergy: 124 Waymouth Street

    2 months ago

    Synergy: 124 Waymouth Street: for for the installation of a tower crane that will require full road closures of Tatham Street, Cannon Street and Eliza Street, and full road and footpath closure of Waymouth Street (between Light Square and Bentham Street) from 7.00 pm, 12 July 2019 to 5.00 pm 14 July 2019*.

    Consultation was open from 19 June to 5pm, 10 July 2019.
    For more information - see below

    Consultation Pack


    Synergy: 124 Waymouth Street: for for the installation of a tower crane that will require full road closures of Tatham Street, Cannon Street and Eliza Street, and full road and footpath closure of Waymouth Street (between Light Square and Bentham Street) from 7.00 pm, 12 July 2019 to 5.00 pm 14 July 2019*.

    Consultation was open from 19 June to 5pm, 10 July 2019.
    For more information - see below

    Consultation Pack


  • Traffic Group Australia: Part Closure of Franklin Street: June 2019

    3 months ago

    Traffic Group Australia for the closure of a section of Franklin Street between King William Street and Bentham Street from 11pm, Friday 21 June to 6pm, Sunday 23 June 2019* for the removal of a tower crane at the GPO Exchange tower, Post Office place

    Consultation is open from 29 May to 19 June 2019.

    Consultation Pack


    Traffic Group Australia for the closure of a section of Franklin Street between King William Street and Bentham Street from 11pm, Friday 21 June to 6pm, Sunday 23 June 2019* for the removal of a tower crane at the GPO Exchange tower, Post Office place

    Consultation is open from 29 May to 19 June 2019.

    Consultation Pack


  • Minuzzo: Road closure of East Terrace directly in front of 217 East Terrace

    4 months ago

    The City of Adelaide (CoA) would like your feedback on applications for a City Works Permit (CWP) submitted by Minuzzo for the road closure of East Terrace directly in front of 217 East Terrace from 7.00 am *10 May 2019 to 6.00 pm 28 March 2020. Consultation is open from 18 April to 9 May 2019.

    Consultation Pack




    The City of Adelaide (CoA) would like your feedback on applications for a City Works Permit (CWP) submitted by Minuzzo for the road closure of East Terrace directly in front of 217 East Terrace from 7.00 am *10 May 2019 to 6.00 pm 28 March 2020. Consultation is open from 18 April to 9 May 2019.

    Consultation Pack




  • Hindmarsh Constructions: Market Street – Consultation opens 6 March and closes 5pm, 27 March 2019

    5 months ago

    For the installation of a tower crane requiring the road closure of Market Street for two days, from 6:00 am 30 March to 6.00 pm 31 March 2019*.

    (*the date and duration of works may be subject to variation at any time).

    Information Pack


    For the installation of a tower crane requiring the road closure of Market Street for two days, from 6:00 am 30 March to 6.00 pm 31 March 2019*.

    (*the date and duration of works may be subject to variation at any time).

    Information Pack


  • Built Environs: Wingfold Tower

    6 months ago

    Built Environs: Wingfold Tower - consultation ran from 13 February to 5pm, 14 March 2019

    • For the installation of a tower crane that requires the road closure of Waymouth Street between Young Street and Tatham Street for two days, from 6.00 am 16 March to 6.00 pm 17 March 2019*.

    Following consultation the crane installation at Wingfold was approved with the date changed to 30th – 31st March 2019.

    For more information view consultation pack.

    Built Environs: Wingfold Tower - consultation ran from 13 February to 5pm, 14 March 2019

    • For the installation of a tower crane that requires the road closure of Waymouth Street between Young Street and Tatham Street for two days, from 6.00 am 16 March to 6.00 pm 17 March 2019*.

    Following consultation the crane installation at Wingfold was approved with the date changed to 30th – 31st March 2019.

    For more information view consultation pack.

  • Built: Dismantling of a Tower Crane at 43 Franklin Street

    6 months ago

    Built: Dismantling of a Tower Crane at 43 Franklin Street opened 27 February 2019 and closed 20 March 2019 for:

    The dismantling of a tower crane requiring the road closure of Franklin Street between Young Street and King William Street for two days, from Midnight *22 March to 6.00 pm 24 March 2019.

    No feedback was received during the consultation period. Permit was approved.

    More information can be seen in the Information Pack and the traffic management plan.


    Built: Dismantling of a Tower Crane at 43 Franklin Street opened 27 February 2019 and closed 20 March 2019 for:

    The dismantling of a tower crane requiring the road closure of Franklin Street between Young Street and King William Street for two days, from Midnight *22 March to 6.00 pm 24 March 2019.

    No feedback was received during the consultation period. Permit was approved.

    More information can be seen in the Information Pack and the traffic management plan.


  • City Works Permit Applications: 116 Waymouth St - Project Update

    7 months ago

    Built Environs: 116 Waymouth Street - consultation opened 13 Feb and closed 5pm, 6 March 2019 - No feedback received - Permit approved.

    • For the installation of construction hoarding at 116 Waymouth Street from 7 March 2019* which requires Playhouse Lane to become a one-way road travelling east, starting from the Playhouse Lane car park (access to and from the car park will be maintained), continuing into Gilles Arcade, and
    • The hoarding and the one-way system remaining in place for the duration of construction until 1 September 2020*.
    For further information (including traffic management plan):

    Consultation Pack

    Built Environs: 116 Waymouth Street - consultation opened 13 Feb and closed 5pm, 6 March 2019 - No feedback received - Permit approved.

    • For the installation of construction hoarding at 116 Waymouth Street from 7 March 2019* which requires Playhouse Lane to become a one-way road travelling east, starting from the Playhouse Lane car park (access to and from the car park will be maintained), continuing into Gilles Arcade, and
    • The hoarding and the one-way system remaining in place for the duration of construction until 1 September 2020*.
    For further information (including traffic management plan):

    Consultation Pack

  • City Works Permit Applications: Toms Court - Project Update

    7 months ago

    Consultation opened 6 February and closed 27 February 2019. One response was received, which supported the permit being approved. No objections were received. The application for the City Works Permits for Synergy Energy: Toms Court has been approved.

    CWP Application

    Synergy Construct: Toms Court

    • For the installation of construction hoarding for the duration of proposed works at 20 Toms Court from 28 February 2019, and
    • The siting of the hoarding during construction. Construction of the hoarding is expected to take two weeks.* The hoarding will remain in place for the duration of...

    Consultation opened 6 February and closed 27 February 2019. One response was received, which supported the permit being approved. No objections were received. The application for the City Works Permits for Synergy Energy: Toms Court has been approved.

    CWP Application

    Synergy Construct: Toms Court

    • For the installation of construction hoarding for the duration of proposed works at 20 Toms Court from 28 February 2019, and
    • The siting of the hoarding during construction. Construction of the hoarding is expected to take two weeks.* The hoarding will remain in place for the duration of the construction work, which is anticipated to be completed by February 2020.*

    (*the date and duration of works may be subject to variation at any time).

    For further information:

    Consultation Pack (which includes the traffic management plan).