City Skate Park

Share City Skate Park on Facebook Share City Skate Park on Twitter Share City Skate Park on Linkedin Email City Skate Park link

Consultation has concluded.

Ariel view of the proposed City Skate Park. The bowl which is predominantly yellow in colour, is clearly visible.

(Image for illustration purposes only)

Update: October 2022

The City Skate Park is officially open!

The Olympic standard skate park will give skateboarders and all wheeled sport enthusiasts a permanent community facility in the CBD. This state-of-the-art facility is a street style space, with stair sets, grinding rails, ledges and a large bowl featuring a unique vertical cradle. It also has a designated area for beginners with a mini bowl, and floodlights to enable safe use throughout day and night.

To find out more, follow the link https://www.cityofadelaide.com.au/city-skate


Update: August 2022

We are almost go for launch! The City skate Park is really taking shape - see below.

The official opening is happening from 10am-12pm on Saturday September 3. At the moment the team is busy applying the finishing touches to the skate park, which will be open to the public from midday on Saturday September 3.


Update: July 2022

We are pleased to announce that construction pf the City Skate Park is almost complete. The final stage will be the landscaping which we will do throughout August. Although the wet month of July did have an impact on progress, we still remain on schedule to have the City Skate Park ready for the official opening on the 1 September. The quality and size of the City Skate Park is truly remarkable considering the adversity faced throughout the construction. We look forward to opening this space for the community on 3 September 2022.


Update: May 2022

The City Skate Park, despite COVID tribulations, is taking shape. Here are some photos which highlight the intricacies of concreting curved structures. Great work by the contractor and to the project team in the delivery of this project!!!


More shots of the work that is currently underway.


Update: April 2022

Progress on the City Skate Park is being made...albeit slowly - see below:


Unfortunately, the spread of Covid 19 across the nation and associated quarantine requirements has led to a reduction in available resources. This has affected the head contractor onsite and key suppliers providing concrete, steel and labour resources. This has inevitably delayed the completion of works and the official opening date.

The contractor has installed the Olympic standard lighting which helps mitigate the delays by working longer hours to complete the project.

Please visit us again soon for further updates.


Update: January 2022

Works at the new City Skate Park are progressing steadily, despite some less than desirable weather conditions leading into Christmas. The civil works are now complete and a lot of footings have been poured in preparation for the skate surface. Over the next two months there will be a continuous flow of concrete occurring in conjunction with the above Olympic standard lighting being installed.’


City Skate Park: Update September 2021

The City of Adelaide has been working to deliver an exemplary skate facility in the heart of the city; however, some unavoidable technical delays have impacted on the project completion date. These unavoidable delays have allowed further testing and optimisation of the remaining works. We understand this has been disappointing, but are confident the final outcome will be worth the wait.

We have done some good work with the contractors for stage one that has allowed us to optimise the earthworks and move into stage two with Convic for the remainder of the build. Convic are a trusted skate park designer and specialist contractor. As the designer they have been working closely with us from the concept stage. Stage two construction is scheduled to begin in early October 2021.

The skate park is on track for completion in early 2022. Please refer to this page for future updates.


City Skate Park - Latest Construction Update 26th April 2021


City Skate Park - Update February 2021

Construction has now commenced on the new City Skate park in Gladys Elphick Park/Narnungga (Park 25). We will be posting updates as construction progresses (see above). Please return here for future updates. Click here to view all previous construction updates.


City Skate Park - Update 2 October 2020

Following extensive investigations at the proposed location of the City Skate Park the concept design has now been completed and detailed design is currently underway. We are aiming for construction of the City Skate Park to begin at Gladys Elphick Park/Narnungga (Park 25) by the end of this year and be completed mid 2021. Click here for more information.

Click here to view the full Concept Design Report. To view a 3D visualisation of the concept design please click on the link below:

You can subscribe for project updates by clicking on the 'STAY INFORMED' button (top right opposite).

Click here for previous project updates.

(Image for illustration purposes only)

Update: October 2022

The City Skate Park is officially open!

The Olympic standard skate park will give skateboarders and all wheeled sport enthusiasts a permanent community facility in the CBD. This state-of-the-art facility is a street style space, with stair sets, grinding rails, ledges and a large bowl featuring a unique vertical cradle. It also has a designated area for beginners with a mini bowl, and floodlights to enable safe use throughout day and night.

To find out more, follow the link https://www.cityofadelaide.com.au/city-skate


Update: August 2022

We are almost go for launch! The City skate Park is really taking shape - see below.

The official opening is happening from 10am-12pm on Saturday September 3. At the moment the team is busy applying the finishing touches to the skate park, which will be open to the public from midday on Saturday September 3.


Update: July 2022

We are pleased to announce that construction pf the City Skate Park is almost complete. The final stage will be the landscaping which we will do throughout August. Although the wet month of July did have an impact on progress, we still remain on schedule to have the City Skate Park ready for the official opening on the 1 September. The quality and size of the City Skate Park is truly remarkable considering the adversity faced throughout the construction. We look forward to opening this space for the community on 3 September 2022.


Update: May 2022

The City Skate Park, despite COVID tribulations, is taking shape. Here are some photos which highlight the intricacies of concreting curved structures. Great work by the contractor and to the project team in the delivery of this project!!!


More shots of the work that is currently underway.


Update: April 2022

Progress on the City Skate Park is being made...albeit slowly - see below:


Unfortunately, the spread of Covid 19 across the nation and associated quarantine requirements has led to a reduction in available resources. This has affected the head contractor onsite and key suppliers providing concrete, steel and labour resources. This has inevitably delayed the completion of works and the official opening date.

The contractor has installed the Olympic standard lighting which helps mitigate the delays by working longer hours to complete the project.

Please visit us again soon for further updates.


Update: January 2022

Works at the new City Skate Park are progressing steadily, despite some less than desirable weather conditions leading into Christmas. The civil works are now complete and a lot of footings have been poured in preparation for the skate surface. Over the next two months there will be a continuous flow of concrete occurring in conjunction with the above Olympic standard lighting being installed.’


City Skate Park: Update September 2021

The City of Adelaide has been working to deliver an exemplary skate facility in the heart of the city; however, some unavoidable technical delays have impacted on the project completion date. These unavoidable delays have allowed further testing and optimisation of the remaining works. We understand this has been disappointing, but are confident the final outcome will be worth the wait.

We have done some good work with the contractors for stage one that has allowed us to optimise the earthworks and move into stage two with Convic for the remainder of the build. Convic are a trusted skate park designer and specialist contractor. As the designer they have been working closely with us from the concept stage. Stage two construction is scheduled to begin in early October 2021.

The skate park is on track for completion in early 2022. Please refer to this page for future updates.


City Skate Park - Latest Construction Update 26th April 2021


City Skate Park - Update February 2021

Construction has now commenced on the new City Skate park in Gladys Elphick Park/Narnungga (Park 25). We will be posting updates as construction progresses (see above). Please return here for future updates. Click here to view all previous construction updates.


City Skate Park - Update 2 October 2020

Following extensive investigations at the proposed location of the City Skate Park the concept design has now been completed and detailed design is currently underway. We are aiming for construction of the City Skate Park to begin at Gladys Elphick Park/Narnungga (Park 25) by the end of this year and be completed mid 2021. Click here for more information.

Click here to view the full Concept Design Report. To view a 3D visualisation of the concept design please click on the link below:

You can subscribe for project updates by clicking on the 'STAY INFORMED' button (top right opposite).

Click here for previous project updates.

Guest Book

Would you like to provide a comment on the City Skate Park? If yes, please write your comment in the space below. Please note that all comments are limited to 255 characters and subject to moderation.

Consultation has concluded.

Can you please provide an update on the skate park?

What's happening? over 2 years ago
characters left

Removed by moderator.

JasonC88 almost 3 years ago
characters left

Also mini ramp would be nice as a popular/safe/fun option

JasonC88 almost 3 years ago
characters left

Hi. Just wondering what's happening with the new skatepark construction?

JasonC88 almost 3 years ago
characters left

More trees, particularity on the north & west side, closer to the edges of the skate facilities so they do shade the skaters. Facilities for a temporary summer shade. Drinking water and toilet facilities.

TanyaRoe over 3 years ago
characters left

I’d like to see a space dedicated to roller skating. Thank you

Tatiana over 4 years ago
characters left

Please include a good drinking / water fountain

Rosslyn over 4 years ago
characters left

As skateparks are heavily used by families often for long periods we would like to see shaded seating with BBQs/water so caregivers can offer healthier food and dont need to access the takeaway shops or negotiate the busy road (often with young children)

Skatepark For Burnside over 4 years ago
characters left

Just build something like http://www.skateboard.com.au/article/11-96856-1/endeavour-hills-freshcret/


It’s the city , it needs to be a large technical park that can be used for comps.

Make the other states jealous

foodgoesinhere over 4 years ago
characters left

A bowl and/or halfpipe, mini or medium size please! And shade for day and night lights would be amazing. Thanks so much for this.

jamesjjcondon over 4 years ago
characters left

would love to see a big old box jump like the big one that use to be at the old city park

justin.d over 4 years ago
characters left

We miss city park! One of the best aspects was the combination of small, technical objects to ride along with larger, more advanced ramps. It kept it interesting after many hours spent riding there. We want some big ramps please! :)

coachkarger over 4 years ago
characters left

It should be a plaza-style skatepark. Being located in the CBD it ought to reflect that. There are already plenty of bowl/ramp skateparks across Adelaide but virtually no plazas. A well-designed mini ramp to the side would tick the box for transition.

rigel over 4 years ago
characters left

What would be most valued n the Adelaide skate scene at the moment Is a purely street style based plaza. There are no parks built in this style with transition almost always being favoured. Transition is great but it would be nice to see some change.

Jakesmallwood over 4 years ago
characters left

Just replicate an existing skatepark!!! There are so many good skateparks in the world, just copy stoner plaza or some other top tier skatepark i dont get how this has not been done already

Pauly88 over 4 years ago
characters left